November 5, 2026

"This needs to be a real return to work on the site." That is how Aspen's chief building official, Bonnie Muhigirwa, put it in September, in a report by Aspen Journalism published in the Aspen Daily News. She was describing the Aspen Club, which closed for redevelopment in 2016 and has not reopened since.

At the end of Ute Avenue, the change is easy to see. A forklift, a crane, an excavator and a skid steer are working around the clubhouse. A site office that was not there in the spring now sits on the property. On a clear weekday you can count about a dozen workers in hard hats.

The 2010 approvals came with a package of public benefits, and every one of them waits on the finished building. One of those benefits, a recreation fund, has an expiration date that does not move.

What December 31 Actually Requires

In mid-April, the city granted the developers another extension on their building permits. Muhigirwa has called this one a "drop-dead" deadline. It lasts through the end of 2026 and comes with two conditions.

  1. "Substantial work" has to continue on the townhome buildings. That means reroofing, framing and flashing, the sheet metal that keeps water out.
  2. If work under the club building permit "has not recommenced by December 31, 2026, the permit will become invalid."

The city also closed a door the project had used before. Asking for land use amendments or filing new change orders will not count as good cause for another extension. In Muhigirwa's words, "it is unlikely that further extension requests will be granted."

This is a real change in how the city treats the site. After a 2024 shutdown that lasted more than half the year, the city had accepted small progress on any part of the project as enough to keep every permit active. Work on the townhomes alone kept the clubhouse permit alive. "Previously, we would see a little bit of electrical work being done, and then nothing for six months, and then another tiny bit of framing," Muhigirwa told Aspen Journalism. "We've said that we're not going to keep that going indefinitely."

The Crew Behind the Fence

The current activity began with a contractor change. Crossland Construction replaced PCL as general contractor of record this summer. In August it sent the city a construction management plan and a schedule covering about four years of work. "We are looking forward to getting this thing rolling," Crossland's construction manager, Austin Soder, wrote to the city in early July.

The building department has seen more than equipment. Muhigirwa confirmed that inspections for concrete slabs in the club building took place in the weeks before the Oct. 25 report. She also said she believes the Dec. 31 deadline is achievable. A site office and a crew do not count as a revival on their own, she said, but the inspections show progress.

The schedule puts these items first this fall:

  • Clubhouse: prep work on the foundation, plus rough plumbing, electrical and heating
  • Townhomes: structural investigations, any corrections they turn up, and water and weatherproofing work

The townhome checks make sense when you look at the buildings. There are 14 partially built townhomes around the edges of the site, and some show weathered siding, missing panels and fractured stonework. Muhigirwa said the city is generally not worried about their structure, and that the new team wants to see how everything has held up.

The schedule's working days follow the city's rules. Aspen's standard construction hours are 7:30 a.m. to 5:30 p.m. on weekdays and 9 a.m. to 5 p.m. on Saturdays. No construction is allowed on Sundays, Thanksgiving Day, Christmas Day or New Year's Day. Between now and the deadline, those rules take two weekdays off the calendar: Thanksgiving on Nov. 26, which is also Aspen Mountain's scheduled opening day, and Christmas Day.

After December, a Schedule Measured in Years

Even if the clubhouse restart satisfies the city, the opening is still years away. Crossland's schedule has more than 2,300 milestones, down to the dates for kitchen countertops and the second coat of paint in an employee locker room. The construction management plan sets these targets for final inspections:

Phase Target for final inspections
Three clusters of townhomes Second quarter of 2029
On-site affordable housing Fourth quarter of 2029
Clubhouse Third quarter of 2030
Final touches across the project Around January 2031

The plan calls the schedule a "living document," and Muhigirwa said it is used for planning and information, not as a binding commitment to dates.

The order of the work matters too. The affordable housing could start later next year, but only after substantial progress on the clubhouse pool. The site logistics plan puts an access ramp and materials staging on top of the workforce housing parcel. Until the pool work is done, the housing has to wait for that space.

What the Neighborhood Was Promised

The Aspen Club ran athletic facilities in a residential zone for nearly 40 years. At its peak it had more than 1,000 members and over 200 employees, with tennis, Pilates, weightlifting, basketball, physical therapy, a pool and a spa. The redevelopment added timeshare lodging, and the city approved it in 2010 in exchange for public benefits written into the approval ordinance. Those conditions still apply, even after a 2015 approval changed the parking and condo layout.

Under the 2010 approval ordinance, the commitments are:

  • Free office space for two nonprofits, continuing the club's history of hosting local organizations
  • Millions of dollars in upgrades to the club's facilities
  • Some community access to the club, whether or not a person is a member
  • 12 two-bedroom affordable units on site, for Aspen Club employees or other workers who qualify through the Aspen-Pitkin County Housing Authority
  • A 0.25% assessment on each fractional-interest sale, paid into a new Community Health and Recreation Fund

All of these depend on a finished building. Aspen Journalism summed it up: "Membership or not, no one can enter a club that doesn't exist."

The One Benefit With an Expiration Date

The recreation fund works differently from the other benefits. It was designed as a backstop. If the club ever stopped providing its community benefits, the fund would pay grants to fill the gap. The assessment is valid for 25 years from the 2010 approval, so the fund sunsets in 2035 whatever happens on the construction site.

The money can only start coming in once sales close, and sales cannot close until units have certificates of occupancy. The project has 14 townhomes and six fractional-ownership condos planned inside the club building, all approved for timeshare use. Under the current schedule, Aspen Journalism estimates the fund could collect for about four years out of a 25-year life.

That is why the December deadline matters to East Aspen. A project that slips can still deliver the clubhouse, the nonprofit offices and the housing later. A late fund simply gets fewer years. When the 2010 ordinance passed, it assumed decades of collections. After a construction closure that was supposed to last less than a year and has now run a decade, the window is down to about four years before the 2035 sunset.

Where to Watch From

The clearest public view of the site is from above. From the Ute Trail, a hiking-only route of 0.9 miles that climbs to an overlook, the club appears as a dirt-brown postage stamp among aspens and evergreens, with the townhomes around the edges and the clubhouse in the middle. From the bike path along the Roaring Fork River, you can see the townhome cluster that is furthest along. The other two sets of townhomes are still under tarps.

For anything more than a view, Crossland plans to post public updates at the site. Its construction management plan names superintendent Braden Scott as "the project liaison and sole point of contact for all public communication relative to the project."

Long-delayed projects like the Aspen Club affect the homes around them, and buyers and sellers on and near Ute Avenue should account for the timeline when they plan. If you own nearby or are considering East Aspen, Carrie Wells can talk through what this project's schedule means for your plans, candidly and in confidence.